Work Profile Report [67W746]
Tenders
Project Activities
Documents
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0- 37510 दि0 12.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
172.27
Resanction Cost :
172.27
Tentative Cost :
172.27
Exp. Upto Last Fy :
27.09
For CFY 2024-2025
Remaining :
145.18
Demand :
50.00
Allotment :
50.00
Exp in CFY :
31.06
Total Up to Date Exp :
58.15
Construction Started
Sanction on : 10 months 4 days ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
60 %
Tentative Completion date on : 5 months 2 weeks ago
28 Feb 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 05-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: