Work Profile Report [67W761]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 60081 दि0 14.03.2024
TS Amount (lakhs) : 569.02 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
226.02
Resanction Cost :
226.02
Tentative Cost :
226.02
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
226.02
Demand :
100.00
Allotment :
150.00
Exp in CFY :
136.36
Total Up to Date Exp :
136.36
Construction Started
Sanction on : 9 months 1 week ago
14 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 03-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand