Work Profile Report [67W788]

दाणौधार मासौ मार्ग के कि0मी0 1 से 3 में डामरकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 37890 दि0 19.07.2027

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

161.60

Resanction Cost :

161.60

Tentative Cost :

161.60

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

161.60

Demand :

71.85

Allotment :

0.02

Exp in CFY :

0.05

Total Up to Date Exp :

0.05

Construction Started

Sanction on : 4 months 4 days ago

19 Jul 2024

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 9 months 4 days from now

28 Aug 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000
Jobs
1
1
0
1
0
0

Remark

view all

कार्य प्रगति पर। -- as on 09-Sep-2024

Rating : 0

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: