Work Profile Report [67W846]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली संख्या 26412 दि0 11.06.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
522.46
Resanction Cost :
522.46
Tentative Cost :
522.46
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
522.46
Demand :
194.48
Allotment :
80.63
Exp in CFY :
80.63
Total Up to Date Exp :
80.63
Construction Started
Sanction on : 7 months 1 week ago
11 Jun 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
30 %
Tentative Completion date on : 7 months 3 days from now
27 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अतिरिक्त पहाड कटान का कार्य 80 प्रतिशत कार्य पूर्ण। जी-1, जी-2, 5 कि0मी0 में पूर्ण। शेष कार्य प्रगति पर। -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: