Work Profile Report [67W887]
Fin Plan
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 327/वा0जि0यो0/सा0पत्रा0/2025-26 दि0 28.05.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
5.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Sanction on : 1 month 2 weeks ago
28 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 5 has been counted as tentative cost increased from to 5 . -- as on 26-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand