Work Profile Report [68W106]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1542/111(2)/09-22(मु0म0 धोषणा)/09 दि0 31.03.2010
TS Amount (lakhs) : 895.79 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
945.00
Resanction Cost :
945.00
Tentative Cost :
945.00
Exp. Upto Last Fy :
712.91
For CFY 2024-2025
Remaining :
232.09
Demand :
130.00
Allotment :
100.00
Exp in CFY :
91.84
Total Up to Date Exp :
804.75
Construction Started
Sanction on : 14 years 5 months ago
31 Mar 2010
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
87 %
Tentative Completion date on : 1 month 1 week from now
28 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मोटर मार्ग के किमी0 8.00 में पार्ट-।। का कार्य पूर्ण एवं किमी0 9.00 में कार्य प्रगति में है। -- as on 11-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: