Work Profile Report [68W275]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : C.E PWD Uttarakhand Dehradun Letter No. 895/07 Yata-PMGSY-N III
TS Amount (lakhs) : 77.91 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.91
Resanction Cost :
77.91
Tentative Cost :
77.91
Exp. Upto Last Fy :
47.84
For CFY 2024-2025
Remaining :
30.07
Demand :
30.07
Allotment :
21.92
Exp in CFY :
29.46
Total Up to Date Exp :
77.30
Work completed
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
30 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 17-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand