Work Profile Report [68W289]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 49552 दिनांक 19/07/2023
TS Amount (lakhs) : 186.08 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
186.08
Resanction Cost :
186.08
Tentative Cost :
186.08
Exp. Upto Last Fy :
38.64
For CFY 2024-2025
Remaining :
147.44
Demand :
60.00
Allotment :
12.00
Exp in CFY :
0.00
Total Up to Date Exp :
38.64
Construction Started
Sanction on : 1 year 1 month ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
22 %
Up to Date :
35 %
Tentative Completion date on : 7 months 1 week from now
01 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिग का कार्य पूर्ण । इण्टर कोट का कार्य प्रगति में हैं -- as on 04-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand