Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.3 | 2.3 | 2.3 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
68W293 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली सं0 48456 दिनांक 14/07/2023
TS Amount (lakhs) : 5.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.89
Resanction Cost :
5.89
Tentative Cost :
5.89
Exp. Upto Last Fy : 2.06
For CFY 2024-2025
Remaining : 3.83
Demand : 3.83
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.06
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
14 Jul 2023
Tentative Completion date:
2 days 6 hours ago
15 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 27-Mar-2024
Physical Peramenters