Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
68W296 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रांक 26505 दिनाँक 08-09-2022
TS Amount (lakhs) : 109.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
109.57
Resanction Cost :
109.57
Tentative Cost :
109.57
Exp. Upto Last Fy : 18.76
For CFY 2024-2025
Remaining : 90.81
Demand : 30.00
Allotment : 23.97
Exp in CFY : 2.16
Total Up to Date Exp : 20.91
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 30 %
Sanction on :
1 year 10 months ago
08 Sep 2022
Tentative Completion date:
4 months 2 weeks from now
05 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिग कोट का कार्य पूर्ण कर लिया है। इण्टर कोट का कार्य प्रगति में है। -- as on 25-Jun-2024
Physical Peramenters