Work Profile Report [68W312]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी पौड़ी के पत्रांक 1156/19/जि0यो0/लो0नि0वि0/2023-24/दिनांक 12 फरवरी 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.91
Resanction Cost :
8.91
Tentative Cost :
8.91
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
8.91
Demand :
8.91
Allotment :
8.91
Exp in CFY :
8.90
Total Up to Date Exp :
8.90
Work completed
Sanction on : 10 months 1 week ago
12 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
100 %
Tentative Completion date on : 5 months 2 weeks ago
08 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 18-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand