Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.5 | 0 |
68W324 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष नियोजन वर्ग लो0नि0वि0 उत्तराखण्ड देहरादून के पत्रांक 388/14 याता0(क)-उ0/2023 दिनांक 15.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.15
Resanction Cost :
24.15
Tentative Cost :
24.15
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 24.15
Demand : 24.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
4 months 2 days ago
15 Mar 2024
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 25-Jun-2024
Physical Peramenters