Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 26412 दिनांक 28 फरवरी 2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
199.49
Resanction Cost :
208.00
Tentative Cost :
208.00
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
207.90
Demand :
184.69
Allotment :
199.39
Exp in CFY :
114.69
Total Up to Date Exp :
114.79
Construction Started
Sanction on : 10 months 3 weeks ago
28 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
75 %
Tentative Completion date on : 2 months 3 weeks from now
15 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाॅप कोड का कार्य पूर्ण । मोसम अनुकूल होते ही पी0सी0 का कार्य प्रारम्भ कर दिया जायेगा। -- as on 15-Jan-2026