Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
68W39 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 508/।।। (2)/ 18-39 (एम0एल0ए0) /2017 दि0 09 फरवरी 2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.71
Resanction Cost :
27.71
Tentative Cost :
27.71
Exp. Upto Last Fy : 26.78
For CFY 2024-2025
Remaining : 0.93
Demand : 0.92
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 26.78
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 years 5 months ago
09 Feb 2018
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Compensation Dispute
अवशेष कास्तकारों को मुआवजा वितरण की कार्यवाही की जा रही है। -- as on 27-Mar-2024
Physical Peramenters