Work Profile Report [68W96]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजला fवकास प्राfधकरण पौडी पत्र सं0 191/डी0डी0ए0-2020-21 fदनंाक 05 जनवरी 2021
TS Amount (lakhs) : 23.1 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.00
Resanction Cost :
50.00
Tentative Cost :
50.00
Exp. Upto Last Fy :
22.19
For CFY 2025-2026
Remaining :
27.81
Demand :
0.00
Allotment :
26.40
Exp in CFY :
26.40
Total Up to Date Exp :
48.60
Construction Started
Sanction on : 4 years 7 months ago
05 Jan 2021
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 4 months 4 weeks ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 31-Mar-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand