Work Profile Report [68W97]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी महोदय पौडी के पत्र सं0 2025/जि०यो० समदिनांकित 2020 दिनांक 06.02.2021 & 339/वा०जि०यो०/व्यय/2023-24 दिनांक 01.07.2023
TS Amount (lakhs) : 189.66 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
200.00
Resanction Cost :
200.00
Tentative Cost :
200.00
Exp. Upto Last Fy :
18.19
For CFY 2024-2025
Remaining :
181.81
Demand :
181.81
Allotment :
181.81
Exp in CFY :
29.58
Total Up to Date Exp :
47.77
Construction Started
Sanction on : 3 years 10 months ago
06 Feb 2021
Physical Progress:
At start of FY 2024-2025 :
3 %
Up to Date :
10 %
Tentative Completion date on : 7 months 5 days from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित कर लिया गया है तथा कार्य प्रगति पर है। -- as on 12-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand