Administrative Approval Detail : शा0सं0 4416/111 (2)/15-04 (मु0म0घो0)/2015 दि0 27.05.2015
TS Amount (lakhs) : 101.98 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
195.62
Resanction Cost :
195.62
Tentative Cost :
195.62
Exp. Upto Last Fy :
107.93
For CFY 2024-2025
Remaining :
87.69
Demand :
50.00
Allotment :
50.00
Exp in CFY :
4.12
Total Up to Date Exp :
112.05
Construction Started
Sanction on : 9 years 5 months ago
27 May 2015
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
65 %
Tentative Completion date on : 2 months 1 week from now
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में है। -- as on 13-Sep-2024
Assets :
Work not linked with IM