Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 14 | 14 | 0.000 | 14 | 0.000 | 0.000 |
69W279 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 501/111(2)/21-38 (एम0एल0ए0)2017 टी0सी0-11 दिनांक 09 मार्च 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14.00
Resanction Cost :
14.00
Tentative Cost :
14.00
Exp. Upto Last Fy : 10.31
For CFY 2024-2025
Remaining : 3.69
Demand : 3.69
Allotment : 3.69
Exp in CFY : 2.97
Total Up to Date Exp : 13.28
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 4 months ago
09 Mar 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान हेतु प्रथम चरण का विस्तृत आगणन गठित कर मुख्य अभि0 के पत्रांक 4684/12 (01)याता (श्रीनगर)-पौड़ी/2021 दि0 05.10.21 द्वारा प्रमुख सचिव लो0नि0 अनुभाग-2, उत्तराखण्ड शासन देहरादून को प्रेषित। उत्तराखण्ड शासन के पत्र ई-पत्रावली सं0 38302 के अनुपालन में कार्यालय मुख्य अभियन्ता स्तर-2 लो0नि0वि0 पौड़ी के पत्रांक 771/01 याता (आगणन)-पौड़ी-2024 दि0 27.04.2024 द्वारा संयुक्त सचिव लो0नि0वि0 अनुभाग-2 देहरादून को प्रेषित। -- as on 21-Mar-2024
Physical Peramenters