Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement |
69W292 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 12(1ं)111(2)/21-38 (एम.एल.ए.)2017 टी0सी0 दि0 03.01.2022
TS Amount (lakhs) : 98.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
98.84
Resanction Cost :
98.84
Tentative Cost :
98.84
Exp. Upto Last Fy : 0.50
For CFY 2024-2025
Remaining : 98.34
Demand : 30.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.50
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 6 months ago
03 Jan 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 08: State Government
Bottelneck: no issue
वर्तमान में प्रस्ताव State govt. स्तर पर लम्बित है। -- as on 03-May-2024
Physical Peramenters