Work Profile Report [69W319]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ाा0सं0 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 111 दि0 16.05.2023
TS Amount (lakhs) : 141.9 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
141.90
Resanction Cost :
141.90
Tentative Cost :
141.90
Exp. Upto Last Fy :
61.41
For CFY 2024-2025
Remaining :
80.49
Demand :
80.49
Allotment :
80.49
Exp in CFY :
44.33
Total Up to Date Exp :
105.73
Work completed
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
100 %
Tentative Completion date on : 6 days 4 hours from now
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण -- as on 02-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: