Work Profile Report [69W338]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई-पत्रावली सं0 36087 लोक निर्माण अनुभाग-2 दि0 30.06.2023
TS Amount (lakhs) : 43.09 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.09
Resanction Cost :
43.09
Tentative Cost :
43.09
Exp. Upto Last Fy :
18.71
For CFY 2024-2025
Remaining :
24.38
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
18.71
Construction Started
Sanction on : 1 year 1 month ago
30 Jun 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on : 1 month 1 week from now
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
G1,G2,G3 का कार्य पूर्ण
PC का कार्य प्रगति पर ।
-- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: