Work Profile Report [69W344]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी का पत्रांक 354/वा0जि0यो0/सा0पत्रा0/2023-24 दिनांक 05 जुलाई 2023
TS Amount (lakhs) : 6 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy :
3.66
For CFY 2024-2025
Remaining :
2.34
Demand :
2.34
Allotment :
2.34
Exp in CFY :
2.14
Total Up to Date Exp :
5.80
Work completed
Sanction on : 1 year 5 months ago
05 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 09-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand