Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
69W364 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 38302 दिनांक 25 अक्टूबर 2023
TS Amount (lakhs) : 121.44 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
121.44
Resanction Cost :
121.44
Tentative Cost :
121.44
Exp. Upto Last Fy : 2.88
For CFY 2024-2025
Remaining : 118.56
Demand : 100.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.88
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
8 months 3 weeks ago
25 Oct 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters