Work Profile Report [69W364]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली सं0 38302 दिनांक 25 अक्टूबर 2023
TS Amount (lakhs) : 121.44 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.44
Resanction Cost :
121.44
Tentative Cost :
121.44
Exp. Upto Last Fy :
2.88
For CFY 2024-2025
Remaining :
118.56
Demand :
100.00
Allotment :
26.99
Exp in CFY :
26.98
Total Up to Date Exp :
29.87
Construction Started
Sanction on : 1 year 4 weeks ago
25 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
25 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी-1 का पूर्ण, जी-2 का कार्य प्रगति पर। -- as on 04-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: