Work Profile

बागेश्वर में मउडियार गवातोली मोटर मार्ग का निर्माण


Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: 60 Meter Span steel girder Motor bridge

Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008

TS Amount (lakhs) : 441 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

441.00

Resanction Cost :

441.00

Tentative Cost :

441.00

Exp. Upto Last Fy : 414.52

For CFY 2024-2025

Remaining : 26.48

Demand : 0.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 414.52

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 60 %

Sanction on :
15 years 11 months ago
25 Jul 2008


Tentative Completion date:
1 year 5 months from now
31 Dec 2025


Actual Completion Date:
Not Yet Reported


Rating : 113

Remark

Forest Status 16: NPV

Bottelneck: Sanction Required form Govt


7.75 किमी पहाड़ कटान एवं पार्ट 2 का कार्य पूर्ण।
पुनरीक्षित आगणन 12 किमी0 हेतु मुख्य अभियंता के पत्र सं0 166/507 याता0-अ0/2023 दिनांक 09.02.2023 द्वारा लागत 525.94 लाख का स्वीकृति हेतु शासन को प्रेषित।
-- as on 14-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 12 12 7.750 4.25 0.000 0.000
Currently only Bank Gaurantee information is avilable