Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 7.750 | 4.25 | 0.000 | 0.000 |
6W125 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: 60 Meter Span steel girder Motor bridge
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 441 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
441.00
Resanction Cost :
441.00
Tentative Cost :
441.00
Exp. Upto Last Fy : 414.52
For CFY 2024-2025
Remaining : 26.48
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 414.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
1 year 5 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 16: NPV
Bottelneck: Sanction Required form Govt
7.75 किमी पहाड़ कटान एवं पार्ट 2 का कार्य पूर्ण।
पुनरीक्षित आगणन 12 किमी0 हेतु मुख्य अभियंता के पत्र सं0 166/507 याता0-अ0/2023 दिनांक 09.02.2023 द्वारा लागत 525.94 लाख का स्वीकृति हेतु शासन को प्रेषित।
-- as on 14-Apr-2024
Physical Peramenters