Work Profile Report [6W183]

जनपद बागेश्वर में असौं से बसकूना तक 4 किमी0 मोटर मार्ग$2सेतु का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : 5150(1)/111(2)/10-18(प्रा0आ0)/2010 दिनांक 16.08.10

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

53.20

Resanction Cost :

53.20

Tentative Cost :

53.20

Exp. Upto Last Fy :

10.45

For CFY 2024-2025

Remaining :

42.75

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

10.45

Phase1 DPR Submitted

Sanction on : 14 years 1 hour ago

16 Aug 2010

Physical Progress:

At start of FY 2024-2025 :

85 %

Up to Date :

85 %

Tentative Completion date on : 11 months 2 weeks from now

31 Jul 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000
Bridge
2
2
0 (0.000m)
2
0 (0.000m)
0 (0.000m)

Remark

view all

मुआवजा वितरण की कार्यवाही की जा रही है। कब्जा सत्यापित किए जाने की कार्यवाही प्रगति पर है। -- as on 04-Aug-2023

Rating : 98

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand