Work Profile Report [6W187]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 7326(1)111(2)/10-18(प्रा0आ0) 2010टी0सी0-बी0आई0 दिनांक 31 दिसम्बर, 2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy :
9.83
For CFY 2024-2025
Remaining :
53.17
Demand :
1.19
Allotment :
1.19
Exp in CFY :
1.19
Total Up to Date Exp :
11.01
Phase1 DPR Submitted
Sanction on : 13 years 10 months ago
31 Dec 2010
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 8 months 1 week from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मुआवजा वितरित किया जाना है। कब्जा सत्यापित किए जाने की कार्यवाही प्रगति पर है। -- as on 04-Aug-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: