Work Profile Report [6W413]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 4417/ंंें111(2)/15-04(मु0मं0घो0)/2015 दिनांक 27.05.2015
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.60
Resanction Cost :
35.60
Tentative Cost :
35.60
Exp. Upto Last Fy :
0.70
For CFY 2025-2026
Remaining :
34.90
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.70
Alignment Approved
Sanction on : 10 years 7 months ago
27 May 2015
Physical Progress:
At start of FY 2025-2026 :
52 %
Up to Date :
52 %
Tentative Completion date on : 9 months 4 weeks from now
31 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधि0अभि0 के पत्राक सं0 2241/2ई दिनांक 12.11.2025 द्वारा पुनः विधिवत स्वीकृति हेतु प्रभा0वना0 बागेश्वर को पत्र लिखा गया है। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: