Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 12 | 12 | 0.000 | 12 | 0.000 | 0.000 |
6W597 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 233(ं।)/।।।(2)/21 -46(एम0एल0ए0)/2017 टी0सी0आई0 दिनांक 15.02.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.88
Resanction Cost :
28.88
Tentative Cost :
28.88
Exp. Upto Last Fy : 2.71
For CFY 2024-2025
Remaining : 26.17
Demand : 2.00
Allotment : 1.14
Exp in CFY : 1.14
Total Up to Date Exp : 3.85
Survey work done
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
3 years 5 months ago
15 Feb 2021
Tentative Completion date:
2 years 5 months from now
31 Dec 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव गठित किया जा रहा है। -- as on 05-Mar-2024
Physical Peramenters