Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
Closed Work 6W604 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Namik Pedestrain Bridge at km 29.120
Administrative Approval Detail : शासनादेश सं0 1397(1)/।।।(2)/21-46(एम0एल0ए0)/2017 दिनांक 25.05.2021
TS Amount (lakhs) : 136.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
136.30
Resanction Cost :
136.30
Tentative Cost :
136.30
Exp. Upto Last Fy : 104.25
For CFY 2024-2025
Remaining : 32.05
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 104.25
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
25 May 2021
Tentative Completion date:
1 year 2 months ago
24 Apr 2023
Actual Completion Date:
1 year 2 months ago
24 Apr 2023
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
कार्य पूर्ण। -- as on 24-Apr-2023
Physical Peramenters