Work Profile Report [6W607]

ग्राम पंचायत कालू में पंचैली गधेरे उन्नू में लगभग 19 मी0 पुलिया का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : dsto letter no 525/जि0यो0(1)/2021-22, dated 05-07-2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

40.00

Resanction Cost :

40.00

Tentative Cost :

40.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

40.00

Demand :

35.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Construction Started

Sanction on : 3 years 1 month ago

05 Jul 2021

Physical Progress:

At start of FY 2024-2025 :

5 %

Up to Date :

5 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
0
0
0
0

Remark

view all

अबटमेंटों का निर्माण कार्य प्रगति पर है। -- as on 01-Apr-2024

Rating : 7

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand