Work Profile Report [6W649]

खर्ककानातोली के बासानी तोक हेतु 60मी0 पैदल झूलापुल के सुपर स्ट्रक्चर का निर्माण कार्यं
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : dsto letter no 525/जि0यो0(1)/2021-22, dated 05-07-2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

60.00

Resanction Cost :

60.00

Tentative Cost :

60.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

60.00

Demand :

20.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Construction Started

Sanction on : 3 years 5 months ago

05 Jul 2021

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 4 months 4 days from now

30 Apr 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
0
0
0
0

Remark

view all

कार्य प्रगति पर। -- as on 20-Nov-2024

Rating : 0

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: