Work Profile

कपकोट के केदारेश्वर मैदान को जाने वाले मुख्य मो0मा0 का निर्माण कार्य।


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

Administrative Approval Detail : dsto letter no 525/जि0यो0(1)/2021-22, dated 05-07-2021

TS Amount (lakhs) : 20 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

20.00

Resanction Cost :

20.00

Tentative Cost :

20.00

Exp. Upto Last Fy : 19.32

For CFY 2024-2025

Remaining : 0.68

Demand : 0.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 19.32

Work completed

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 100 %

Sanction on :
3 years 1 week ago
05 Jul 2021


Tentative Completion date:
2 years 7 months ago
12 Dec 2021


Actual Completion Date:
2 years 3 months ago
25 Mar 2022


Rating : 100

Remark

Bottelneck:


कार्य पूर्ण। -- as on 14-Dec-2021

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 1 0
Currently only Bank Gaurantee information is avilable