Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
6W691 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: 60 Mtr Span Suspantion Bridge Poling
Administrative Approval Detail : ‘शा.सं. 5723(1)/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0 ।।। दिनांक 29.11.2021
TS Amount (lakhs) : 113.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
113.77
Resanction Cost :
113.77
Tentative Cost :
113.77
Exp. Upto Last Fy : 104.75
For CFY 2024-2025
Remaining : 9.02
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 104.75
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
29 Nov 2021
Tentative Completion date:
6 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
6 months 4 weeks ago
18 Dec 2023
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
कार्य पूर्ण। पी0सी0आर0 गठित की जा रही है। -- as on 12-Apr-2024
Physical Peramenters