Work Profile Report [6W691]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ‘शा.सं. 5723(1)/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0 ।।। दिनांक 29.11.2021
TS Amount (lakhs) : 113.77 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
113.77
Resanction Cost :
113.77
Tentative Cost :
108.00
Saving
5.77
Exp. Upto Last Fy :
104.94
For CFY 2025-2026
Remaining :
8.83
Demand :
1.00
Allotment :
0.33
Exp in CFY :
0.33
Total Up to Date Exp :
105.27
In Maintenance After Completion
Sanction on : 4 years 2 weeks ago
29 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 11 months ago
31 Dec 2023
Actual Completion Date : 1 year 11 months ago
18 Dec 2023
Physical Linear Components
Remark
Overall Saving 5.77 has been recorded as expected cost of work reduced from 113.77 to 108 . -- as on 09-Dec-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: 60 Mtr Span Suspantion Bridge Poling