Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
6W740 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 50154 दिनांक 28.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 4.40
Demand : 1.00
Allotment : 2.17
Exp in CFY : 2.17
Total Up to Date Exp : 2.27
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
1 year 5 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भूवैज्ञानिक निरीक्षण दिनांक 05.03.2024 को पूर्ण। आख्या अपेक्षित है। समरेखण प्रस्ताव गठित किया जाना है। -- as on 28-Apr-2024
Physical Peramenters