Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
6W771 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय जिला आपदा प्रबंधन प्राधिकरण के पत्र सं0 500/तेरह-डी0डी0एम0ए0/2022-23 दिनांक 11.10.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.25
Resanction Cost :
5.25
Tentative Cost :
5.25
Exp. Upto Last Fy : 2.60
For CFY 2024-2025
Remaining : 2.65
Demand : 2.65
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.60
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
11 Oct 2022
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 3 months ago
31 Mar 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 12-May-2023
Physical Peramenters