Work Profile

ग्राम पंचायत बोरबलडा से मातोली तक पर्यटकों हेतु खडंजा मार्ग का निर्माण।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 10.00 Lacs

Resanction Cost : 10.00 Lacs

Exp. Upto Last Fy : 3.56 Lacs

For CFY 2024-2025

Remaining : 6.44 Lacs

Demand : 6.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 3.56 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 45 %

Up to Date : 100 %

Sanction on :
10 months 3 weeks ago
06 Jul 2023


Tentative Completion date:
4 months 4 weeks from now
31 Oct 2024


Actual Completion Date:
Not Yet Reported


Rating : 207

Remark

Bottelneck: no issue


कार्य पूर्ण। -- as on 01-Jun-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 0 1 1 1
Currently only Bank Gaurantee information is avilable