Work Profile Report [6W849]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0-ई0 पत्रावली से0 48456 दिनांक 15.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
231.34
Resanction Cost :
231.34
Tentative Cost :
231.34
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
231.34
Demand :
231.00
Allotment :
18.84
Exp in CFY :
18.84
Total Up to Date Exp :
18.84
Construction Started
Sanction on : 1 year 1 week ago
15 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
3 %
Up to Date :
40 %
Tentative Completion date on : 1 week 5 days ago
11 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डिफेक्ट कटिंग का कार्य पूर्ण। दीवारों का कार्य पूर्ण।
पी0सी0 का कार्य प्रगति पर।
-- as on 12-Oct-2024