Work Profile Report [6W852]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइत संख्या 51057 दिनांक 07.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.00
Resanction Cost :
6.00
Tentative Cost :
6.00
Exp. Upto Last Fy :
0.15
For CFY 2024-2025
Remaining :
5.85
Demand :
2.26
Allotment :
0.88
Exp in CFY :
0.88
Total Up to Date Exp :
1.03
Survey work done
Sanction on : 1 year 2 weeks ago
07 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
15 %
Tentative Completion date on : 8 months 1 week from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण प्रस्ताव इस कार्यालय के पत्र सं0 2374/1सी0 दिनांक 21.10.2024 द्वारा अनुमोदन हेतु अधीक्षण अभियंता को प्रेषित। -- as on 23-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: