Work Profile Report [6W856]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0-5082/।।।(2)/2023-01(प्रा0आ0)/2023 दिनांक 09.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
379.37
Resanction Cost :
379.37
Tentative Cost :
379.37
Exp. Upto Last Fy :
209.63
For CFY 2024-2025
Remaining :
169.74
Demand :
158.10
Allotment :
138.10
Exp in CFY :
142.80
Total Up to Date Exp :
352.43
Construction Started
Sanction on : 9 months 1 week ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
50 %
Tentative Completion date on : 1 week 4 days ago
05 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रश बैरियर का कार्य प्रगति पर। -- as on 21-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: