Work Profile Report [6W858]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : आवास अनुभाग-2 उत्तराखण्ड शासन के ई पत्रावली सं0 33412 दिनांक 19.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.24
Resanction Cost :
46.24
Tentative Cost :
46.24
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
46.24
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 9 months 4 weeks ago
19 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
10 %
Tentative Completion date on : 11 months 2 weeks from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण कार्य प्रगति पर है। -- as on 02-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand