Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 68.04 | 68.04 | 0.000 | 68.04 | 0.000 | 0.000 |
6W874 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइत संख्या 30290/46 दिनांक 24.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.82
Resanction Cost :
40.82
Tentative Cost :
40.82
Exp. Upto Last Fy : 0.15
For CFY 2024-2025
Remaining : 40.67
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.15
Survey work done
Physical Progress:
At start of FY 2024-2025 : 3 %
Up to Date : 3 %
Sanction on :
5 months 3 weeks ago
24 Jan 2024
Tentative Completion date:
1 year 10 months from now
31 May 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य प्रगति पर। -- as on 29-Mar-2024
Physical Peramenters