Work Profile Report [6W889]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0-ई पत्रावली सं0 56385 दिनांक 15.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
78.86
Resanction Cost :
78.86
Tentative Cost :
78.86
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
78.86
Demand :
72.64
Allotment :
0.00
Exp in CFY :
48.37
Total Up to Date Exp :
48.37
Construction Started
Sanction on : 8 months 1 week ago
15 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
95 %
Tentative Completion date on : 6 days 3 hours from now
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रश बैरियर एवं पैरापिटों का कार्य पूर्ण। डेलीनेटर का कार्य प्रगति पर। -- as on 23-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: