Work Profile Report [6W970]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागेश्वर के पत्र सं0 115/जि0यो0/2024-25 दिनांक 25.02.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.00
Resanction Cost :
25.00
Tentative Cost :
25.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
25.00
Demand :
24.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 9 months 2 weeks ago
25 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
5 %
Tentative Completion date on : 2 months 4 weeks from now
15 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: