Work Profile Report [6W997]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई फाइल सं0 68052/46 दिनांक 04.08.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
126.03
Resanction Cost :
126.03
Tentative Cost :
74.00
Saving
52.03
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
126.03
Demand :
73.21
Allotment :
12.31
Exp in CFY :
12.31
Total Up to Date Exp :
12.31
Construction Started
Sanction on : 4 months 1 week ago
04 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 8 months 3 weeks from now
11 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.50 किमी0 पहाड़ कटान पूर्ण।
कार्य प्रगति पर।
-- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: