Work Profile Report [70W130]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : 1440/।।। (2)/11-05 (प्रा0आ0)/2010
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy :
18.99
For CFY 2024-2025
Remaining :
18.81
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
18.99
Work completed
Sanction on : 13 years 4 months ago
28 Mar 2011
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
31 Mar 2024
Actual Completion Date : 1 year 4 months ago
31 Mar 2023
Physical Linear Components
Remark
संरेखण स्वीकृत। प्रथम चरण के कार्य लगभग पूर्ण I मुआवजा भुगतान किया जा चुका है। -- as on 03-Jan-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: