Work Profile Report [70W141]

ग्राम च्वारा से मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : fजलाfधकारी पौड़ी के पत्रांक 1058/fज0यो0/ लो0fन0fव0/2016-17 fद0 31.08.2016

TS Amount (lakhs) : 44.66 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

44.66

Resanction Cost :

44.66

Tentative Cost :

44.66

Exp. Upto Last Fy :

12.61

For CFY 2024-2025

Remaining :

32.05

Demand :

30.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

12.61

Construction Started

Sanction on : 7 years 11 months ago

31 Aug 2016

Physical Progress:

At start of FY 2024-2025 :

50 %

Up to Date :

50 %

Tentative Completion date on : 4 months 2 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
0.9
0.9
0.400
0.5
0.400
0.000

Remark

view all

400मी0 में कार्य पूर्ण । शेष 500 मी0 में ग्रामीण निर्माण विभाग द्वारा कार्य कराया जा रहा है। -- as on 28-Mar-2024

Rating : 50

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: