Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
70W143 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 7235/111(2)/11-139(प्रा0आ0)/2011 दिनांक 24.12.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy : 24.57
For CFY 2024-2025
Remaining : 25.83
Demand : 4.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 24.57
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
12 years 6 months ago
24 Dec 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
संरेखण स्वीकृत । विस्तृत आगणन नई दरों पर गठित कर अधीक्षण अभियन्ता पौड़ी को प्रेषित। मुआवजा भुगतान अवशेष। -- as on 28-Mar-2024
Physical Peramenters