Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
70W213 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी/मुख्य fवकास अfधकारी के पत्रांक 859 /वा0fज0यो0/2018-19 fद0 14.08.2018
TS Amount (lakhs) : 19.44 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
20.00
Resanction Cost :
20.00
Tentative Cost :
20.00
Exp. Upto Last Fy : 5.80
For CFY 2024-2025
Remaining : 14.20
Demand : 14.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.80
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 11 months ago
14 Aug 2018
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
28 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 30-Jan-2024