Work Profile Report [70W223]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5341/।।।(2)/18-36(एम0एल0ए0)/ 201 /टी0सी0 दि0 02.11.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.80
Resanction Cost :
39.80
Tentative Cost :
39.80
Exp. Upto Last Fy :
12.93
For CFY 2024-2025
Remaining :
26.87
Demand :
6.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
12.93
Construction Started
Sanction on : 6 years 3 weeks ago
02 Nov 2018
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
40 %
Tentative Completion date on : 4 months 3 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त। मुआवजा गठन की कार्यवाही की जा रही है। -- as on 03-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: