Work Profile Report [70W24]

जनपद पौड़ी गढ़वाल के विकासखण्ड नैनीड़ांडा के अन्तर्गत अपोला गांव से अपोलोसेरा नलय तक सड़क निर्माण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 4842(1)/।।।(2)/।।-30 (एम0एल0ए0)/2011

TS Amount (lakhs) : 33.35 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.40

Resanction Cost :

50.40

Tentative Cost :

50.40

Exp. Upto Last Fy :

39.21

For CFY 2024-2025

Remaining :

11.19

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

39.21

Construction Started

Sanction on : 13 years 1 month ago

01 Oct 2011

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000

Remark

view all

डी0पी0आर0 द्वितीय चरण स्टेज-1 हेतु स्वीकृत है। मुआवजा भुगतान अवशेष है। -- as on 23-Jul-2024

Rating : 82

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: